Construction within the city is set to begin June 29th and Complete on July 28th. The anticipated durations and dates are the following;
- Chip Seal Application – June 29th – July 20th (14 Days)
- Flush Coat Application – July 21st – July 28th (7 Days)
- 1000 W; SR-102 (Mainstreet) to 1000 N – Roto-Mill and Pave – July 12th – July 19th (6 Days)
Why is the road repair for 1000 N. West of 2300 W. not included?
Is it going to be done this year, as we were told in the past city council meetings?
If not, what is the excuse this time?
I am sure there are quite a few Tremonton residents & voters that are tired of their cars being ‘Beat-Up’ by that road.