Construction within the city is set to begin June 29th and Complete on July 28th. The anticipated durations and dates are the following;

 

  • Chip Seal Application – June 29th – July 20th (14 Days)
  • Flush Coat Application –  July 21st – July 28th (7 Days)
  • 1000 W; SR-102 (Mainstreet) to 1000 N – Roto-Mill and Pave – July 12th – July 19th (6 Days)

 