UDOT to Close SR-102 Bridge over I-84

Closure Begins Saturday, May 31, 2025

 

SR-102 Bridge over I-84 – Tremonton/Bothwell Interchange (Exit 40)

 

Starting at 6 a.m. on Saturday, May 31, UDOT will fully close the SR-102 Bridge over I-84 to begin a complete bridge deck replacement. This full closure will remain in place through August 24, 2025.

 

Freeway Closure: I-84 will close nightly in both directions from 10 p.m. to 6 a.m., June 2-6 for demolition activities. Plan for moderate delays.

 

This bridge work will be completed using a single, continuous monolithic pour, which minimizes joints and improves long-term strength, durability, and construction efficiency.

 

What to Expect:

 

·     Bridge fully closed over I-84 from May 31 to August 24

·     Northbound I-84 on- and off-ramps will remain open

·     Southbound I-84 traffic will be detoured via I-15 (see map below)

 

Please plan ahead and allow extra travel time to follow the posted detour.

 

Thank you for your patience as we work to improve Utah’s infrastructure.

 

 

Project Background

 

Project Background

Three bridges over I-84 in Box Elder County have been identified for necessary maintenance, repair, or full replacement. UDOT is committed to maintaining the safety and reliability of bridges throughout the state.

 

Stay Connected

 

For more information and to stay updated on these bridge improvements, we invite you to contact our public information team at 800-292-3557 or visit the project website at udotinput.utah.gov/boxelderbridges. To sign up for email updates with the latest news and announcements about the project – simply send an email to boxelderbridges@utah.gov with “Box Elder Bridges” in the subject line.

 

There are several other regional projects taking place this construction season.

For the latest information regarding this and other UDOT construction

projects, download the free UDOT Traffic app on any iPhone or

Android device or visit udottraffic.utah.gov.

 

 

For More Project Information

Hotline: 800-292-3557

Email: boxelderbridges@utah.gov

Website: udotinput.utah.gov/boxelderbridges