Street Projects 2023
Construction within the city is set to begin June 29th and Complete on July 28th. The anticipated durations and dates are the following; Chip Seal Application – June 29th – July 20th (14 Days) Flush Coat Application – July 21st – July 28th (7 Days) 1000 W; SR-102 (Mainstreet) to 1000 N – [...]